Latest Projects
Chiswell Green
New Build
-
The Site
-
The ground was reduced sufficiently to position the house at the correct level. The perimeter will be landscaped during the house construction.
-
Footings
-
The footings being set out to the layout of the new house.
The ground floor beam and block floor slab were fitted next.
-
Blockwork
-
Progress on site showing the implementation of the steelwork and erection of the facing brickwork and blockwork on the ground floor.
-
Roof timbers
-
Progress on site showing the completion of the blockwork to roof level and the roof timbers being put in place.
-
Roof tiles
-
The roof is complete with the velux windows in place.
-
Commenced December 2009
-
A new build 4 bedroom detached house.